Overhaul of the bridge in Grodno on Popovich Street: spans are being concreted

Overhaul of the bridge in Grodno on Popovich Street: spans are being concreted

26 January , Grodno / Corr.. Belta/. In Grodno, work continues on the overhaul of the bridge on the street. Popovich. This was reported to a BelTA correspondent by the press service of the Grodno Regional Executive Committee..

“At this stage, one of the spans is being poured with concrete.. The dismantling of the asphalt concrete pavement has already been completed at the facility., protective layer, railings and sidewalk blocks. Completed works on disconnection of engineering networks, drilling holes in a monolithic slab for anchors. Done70% span drilling1, 2, 4, 6, 7, 8 for the installation of a monolithic slab of the bridge deck”, – told in the regional executive committee.

Also tight100% prestressing reinforcement(bundles) on span structures No.3 and5. The protective layer of the bridge deck was dismantled. Special auxiliary structures and devices were made at the seams of superstructures2-3, 3-4, 4-5 and5-6. Concreting of a monolithic slab of a concrete structure and beams was completed.

To organize the movement of pedestrians, a pontoon ferry was opened near the bridge under repair. 25 January it was increased by7 meters due to the predicted flood situation.-0-